On the minimum cost project schedule
J. Kamburowski
Omega, 1995, vol. 23, issue 4, 463-465
Abstract:
This note draws attention to and corrects an error, which repeats that made in the so-called 'crashing algorithm' given in many textbooks, in a note by Wu and Li on minimal cost project networks published in Omega 22(4), 401-407, in 1994.
Keywords: PERT; project; management (search for similar items in EconPapers)
Date: 1995
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (3)
Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/0305-0483(95)00028-M
Full text for ScienceDirect subscribers only
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eee:jomega:v:23:y:1995:i:4:p:463-465
Ordering information: This journal article can be ordered from
http://www.elsevier.com/wps/find/supportfaq.cws_home/regional
https://shop.elsevie ... _01_ooc_1&version=01
Access Statistics for this article
Omega is currently edited by B. Lev
More articles in Omega from Elsevier
Bibliographic data for series maintained by Catherine Liu ().