Revisiting reliability of estimates at completion for department of defense contracts
Deborah B. Kim,
Edward D. White,
Jonathan D. Ritschel and
Chad A. Millette
Journal of Public Procurement, 2019, vol. 19, issue 3, 186-200
Abstract:
Purpose - Within earned value management, the cost performance index (CPI) and the critical ratio (CR) are used to generate the estimates at completion (EACs). According to the research in the 1990s, estimating the final contract’s cost at completion (CAC) using EACCRis a quicker predictor of the actual final cost versus using EACCPI. This paper aims to investigate whether this trend stills holds for modern department of defense contracts. Design/methodology/approach - Accessing the Cost Assessment Data Enterprise (CADE) database, 451 contracts consisting of 863 contract line item numbers (CLINs) were initially retrieved and analyzed in three stages. The first replicated the work conducted in 1990s. The second stage entailed calculating 95 per cent confidence intervals and hypothesis tests regarding percentage accuracy of EACs for a contract’s final CAC. Lastly, regression analysis was conducted to characterize major, moderate and minor influencers on EAC reliability. Findings - For modern contracts, EACCRaligns more with EACCPIand no longer demonstrates early accuracy of a contract’s final CAC. Contract percentage completion strongly reduced the per cent error of estimating CAC, while cost-plus-fixed-fee contracts and those with no work breakdown structure greater than Level 2 negatively affected accuracy. Social implications - To militate against optimism of early assessment of a contract's true cost. Originality/value - This paper provides empirical evidence that EACCRbehaves more like EACCPIwith respect to modern contracts, suggesting that today’s contracts have relatively high SPI. Therefore, caution is warranted for program managers when estimating the CAC from contract initiation up to and slightly beyond the mid-point of completion.
Keywords: Earned value management; Estimate at completion (EAC); Per cent complete; EAC stability (search for similar items in EconPapers)
Date: 2019
References: Add references at CitEc
Citations:
Downloads: (external link)
https://www.emerald.com/insight/content/doi/10.110 ... d&utm_campaign=repec (text/html)
https://www.emerald.com/insight/content/doi/10.110 ... d&utm_campaign=repec (application/pdf)
Access to full text is restricted to subscribers
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eme:jopppp:jopp-02-2018-0006
DOI: 10.1108/JOPP-02-2018-0006
Access Statistics for this article
Journal of Public Procurement is currently edited by Mr David Loseby
More articles in Journal of Public Procurement from Emerald Group Publishing Limited
Bibliographic data for series maintained by Emerald Support ().