Quantitative Analysis of Waiting Length and Waiting Time for Frame Construction Work Activities Using a Queue Model; Focusing on Korean Apartment Construction

Jin-Won Kim, Namhyuk Ham and Jae-Jun Kim
Additional contact information
Jin-Won Kim: Department of Architectural Engineering, Hanyang University, 222, Wangsimni-ro, Seongdong-gu, Seoul 04763, Korea
Namhyuk Ham: Department of Digital Architecture and Urban Engineering, Hanyang Cyber University, 220, Wangsimni-ro, Seongdong-gu, Seoul 04763, Korea
Jae-Jun Kim: Department of Architectural Engineering, Hanyang University, 222, Wangsimni-ro, Seongdong-gu, Seoul 04763, Korea

Sustainability, 2021, vol. 13, issue 7, 1-13

Abstract: The frame construction of an apartment complex that consists of multiple buildings encounters various uncertainties, owing to the complex relationships between units of work. Currently, the period of such a construction is calculated based on the number of floors of the highest building in the complex. This study quantitatively analyzes an apartment frame construction period using a queue model and evaluates the validity of the estimated period. In this regard, a methodology is proposed for analyzing the construction period by applying the concept of a customer and a server. A case study on the duration of an apartment frame construction period is conducted with the Korea Land and Housing Corporation, which has supplied the largest number of apartments in South Korea. It was found that the stable state of a queue system was observed when the rate of server utilization was applied to the basement and above-ground floors. However, a stable state was not reached on the ground floor. This study includes non-working days in its calculation and quantitatively analyzes uncertainty factors during construction. Therefore, the findings can be practically utilized to quantitatively plan the durations of work units in an apartment frame construction.

Keywords: frame construction; multiple buildings; construction period; uncertainty factors; queue model (search for similar items in EconPapers)
JEL-codes: O13 Q Q0 Q2 Q3 Q5 Q56 (search for similar items in EconPapers)
Date: 2021
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (1)

Downloads: (external link)
https://www.mdpi.com/2071-1050/13/7/3778/pdf (application/pdf)
https://www.mdpi.com/2071-1050/13/7/3778/ (text/html)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:gam:jsusta:v:13:y:2021:i:7:p:3778-:d:526102

Access Statistics for this article

Sustainability is currently edited by Ms. Alexandra Wu

More articles in Sustainability from MDPI
Bibliographic data for series maintained by MDPI Indexing Manager ().

 
Page updated 2025-03-19
Handle: RePEc:gam:jsusta:v:13:y:2021:i:7:p:3778-:d:526102