EconPapers    
Economics at your fingertips  
 

Calculation Method for Investigating the Behavior of Ground Surface Settlement of Underpass Buildings in TBM Double-Line Tunnels

Ting Ren, Hailong Zhang (), Yuancheng Guo, Yang Tang, Qinglin Li and Seisuke Okubo
Additional contact information
Ting Ren: School of Civil Engineering, Chongqing Three Gorges University, Chongqing 404020, China
Hailong Zhang: School of Civil Engineering, Chongqing University of Arts and Sciences, Chongqing 402160, China
Yuancheng Guo: School of Civil Engineering, Chongqing Three Gorges University, Chongqing 404020, China
Yang Tang: School of Civil Engineering, Chongqing University of Arts and Sciences, Chongqing 402160, China
Qinglin Li: School of Resources and Security, Chongqing University, Chongqing 400045, China
Seisuke Okubo: Department of Geo-System Engineering, The University of Tokyo, Tokyo 113-8656, Japan

Sustainability, 2022, vol. 14, issue 20, 1-14

Abstract: This study aims to investigate the behavior of ground surface settlement in TBM double-line tunnels constructed under existing buildings and to devise a calculative representation for that behavior. Numerical simulation and field monitoring methods were used to examine the Zhongcong Tunnel in Chongqing Metro Line 9. The ground surface settlement was analyzed using an orthogonal test of 3D numerical simulation methods. The results showed that ground surface settlement was influenced by TBM tunneling parameters and the location of the existing building in the following manner. The existing building reduced the settlement trough width. Surface settlement was increased by frictional and palm surface thrust forces but reduced by grouting pressure. The settlement trough width of the first excavation i z correlated with that of the last excavation i y . To accommodate the influence of existing buildings, the tilt factor of the settlement trough T R was introduced to improve the formula for calculating the ground surface settlement of TBM double-line tunnels. The improved formula was validated by comparing the calculated results with actual measurements.

Keywords: TBM double-line tunnel; tunneling parameters; underpass existing buildings; ground surface settlement; calculation method; orthogonal experiments (search for similar items in EconPapers)
JEL-codes: O13 Q Q0 Q2 Q3 Q5 Q56 (search for similar items in EconPapers)
Date: 2022
References: View references in EconPapers View complete reference list from CitEc
Citations:

Downloads: (external link)
https://www.mdpi.com/2071-1050/14/20/13410/pdf (application/pdf)
https://www.mdpi.com/2071-1050/14/20/13410/ (text/html)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:gam:jsusta:v:14:y:2022:i:20:p:13410-:d:945824

Access Statistics for this article

Sustainability is currently edited by Ms. Alexandra Wu

More articles in Sustainability from MDPI
Bibliographic data for series maintained by MDPI Indexing Manager ().

 
Page updated 2025-03-19
Handle: RePEc:gam:jsusta:v:14:y:2022:i:20:p:13410-:d:945824