Development of Delay and Disruption Cause Monitoring Framework for Megaprojects: A Claim Management Approach from the Contractor’s Perspective to Enhance Sustainability in the Built Environment
Ozan Okudan,
Murat Çevikbaş () and
Zeynep Işık
Additional contact information
Ozan Okudan: Department of Civil Engineering, Yıldız Technical University, Davutpaşa Caddesi, 34220 Istanbul, Turkey
Murat Çevikbaş: Department of Civil Engineering, Isparta University of Applied Sciences, 32260 Isparta, Turkey
Zeynep Işık: Department of Civil Engineering, Yıldız Technical University, Davutpaşa Caddesi, 34220 Istanbul, Turkey
Sustainability, 2024, vol. 16, issue 24, 1-24
Abstract:
Delays and disruptions (D&D) are considered chronic peculiarities of the construction phase of the built environment, especially in megaprojects. Systematic monitoring of claimable D&D causes becomes crucial for the contractors to compensate for their losses caused by delays and disruptions, enabling sustainable use of resources. Thus, this study proposed a delay and disruption (D&D) cause monitoring framework that enables contractors to timely and accurately detect claimable delays and disruption causes/events in megaprojects. At the outset, a systematic literature review was conducted to design an initial version of the framework and extract claimable D&D. Then, focus group discussion (FGD) sessions were conducted to revise and refine the initial version of the framework and a list of claimable D&D causes. Next, a fuzzy Analytical Hierarchy Process (AHP) analysis was conducted to determine the relative importance of each claimable D&D cause in terms of its impact on the megaprojects. Finally, a consistency analysis was conducted to demonstrate the reliability of the dataset. Findings revealed that claimable D&D causes are indispensable parts of the claim management process. In this manner, the proposed framework recommends monitoring the claimable D&D causes regularly during the whole construction phase of the megaprojects. The fuzzy AHP analysis also revealed that causes such as “Suspension of project activities by the owner”, “Errors and clashes in the design”, “Shortage of construction materials in the market”, “Discovery of fossils and historical artifacts”, “Unavailability of the commissioning team on the due date”, and “Late delivery of testing materials and utilities by the owner” were particularly rated as highly critical causes, needing urgent and sophisticated monitoring plan for timely detection and data collection. By introducing a proactive approach to avoid lengthy and costly dispute resolution processes, this study enables decision-makers to enhance sustainability in the built environment.
Keywords: built environment; sustainable development; sustainable project management; sustainable infrastructure; megaprojects; delay management; disruption management; claim management; fuzzy AHP; MCDM (search for similar items in EconPapers)
JEL-codes: O13 Q Q0 Q2 Q3 Q5 Q56 (search for similar items in EconPapers)
Date: 2024
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
https://www.mdpi.com/2071-1050/16/24/10856/pdf (application/pdf)
https://www.mdpi.com/2071-1050/16/24/10856/ (text/html)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:gam:jsusta:v:16:y:2024:i:24:p:10856-:d:1541602
Access Statistics for this article
Sustainability is currently edited by Ms. Alexandra Wu
More articles in Sustainability from MDPI
Bibliographic data for series maintained by MDPI Indexing Manager ().