BIM-Based 4D Simulation to Improve Module Manufacturing Productivity for Sustainable Building Projects
Joosung Lee and
Jaejun Kim
Additional contact information
Joosung Lee: Department of Architectural Engineering, Graduate School, Hanyang University, 222 Wangsimri-ro, Seongdonggu, Seoul 04763, Korea
Jaejun Kim: Department of Architectural Engineering, Hanyang University, 222 Wangsimri-ro, Seongdonggu, Seoul 04763, Korea
Sustainability, 2017, vol. 9, issue 3, 1-23
Abstract:
Modular construction methods, where products are manufactured beforehand in a factory and then transported to the site for installation, are becoming increasingly popular for construction projects in many countries as this method facilitates the use of the advanced technologies that support sustainability in building projects. This approach requires dual factory–site process management to be carefully coordinated and the factory module manufacturing process must therefore be managed in a detailed and quantitative manner. However, currently, the limited algorithms available to support this process are based on mathematical methodologies that do not consider the complex mix of equipment, factories, personnel, and materials involved. This paper presents three new building information modeling-based 4D simulation frameworks to manage the three elements—process, quantity, and quality—that determine the productivity of factory module manufacturing. These frameworks leverage the advantages of 4D simulation and provide more precise information than existing conventional documents. By utilizing a 4D model that facilitates the visualization of a wide range of data variables, manufacturers can plan the module manufacturing process in detail and fully understand the material, equipment, and workflow needed to accomplish the manufacturing tasks. Managers can also access information about material quantities for each process and use this information for earned value management, warehousing/storage, fabrication, and assembly planning. By having a 4D view that connects 2D drawing models, manufacturing errors and rework can be minimized and problems such as construction delays, quality lapses, and cost overruns vastly reduced.
Keywords: Building information modeling; 4D simulation; sustainability; operation level 4D model; modular construction; schedule management; material quantity management; quality management (search for similar items in EconPapers)
JEL-codes: O13 Q Q0 Q2 Q3 Q5 Q56 (search for similar items in EconPapers)
Date: 2017
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (7)
Downloads: (external link)
https://www.mdpi.com/2071-1050/9/3/426/pdf (application/pdf)
https://www.mdpi.com/2071-1050/9/3/426/ (text/html)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:gam:jsusta:v:9:y:2017:i:3:p:426-:d:92928
Access Statistics for this article
Sustainability is currently edited by Ms. Alexandra Wu
More articles in Sustainability from MDPI
Bibliographic data for series maintained by MDPI Indexing Manager ().