Fuzzy critical chain risk management for quantifying impact of variation in non-critical activity duration on project duration
Thoedtida Thipparate
International Journal of Project Organisation and Management, 2014, vol. 6, issue 1/2, 48-66
Abstract:
This paper develops a method for quantifying and minimising risks causing variation in critical and non-critical activity duration which influences a project completion time. The method employs a critical chain concept using buffer penetration rate to control risk affecting activities in construction projects. Uncertainty associated with the risk assessment and variation in activity duration is represented by fuzzy numbers. The buffer of several types is sized based on the variation in activity duration which is in direct proportion to the assessed value of risk magnitude. The proposed method shows relationships of the scheduled buffer, consumed buffer and project completion time which helps tackle variation in both critical and non-critical chains and reduce the impact of the non-critical chains on the critical chain. It provides a design chart for a project manager for developing an as-planned schedule with a consideration of risks. During project execution, the proposed method concentrates on the penetration level in the project and feeding buffers and dynamically updates an as-built schedule based on actual progress, which can be also used as a schedule control.
Keywords: critical chain project management; CCPM; FAHP; analytical hierarchy process; fuzzy AHP; non-critical activities; project risk management; variation impact; project completion time; buffer penetration rate; construction projects; uncertainty; risk assessment; scheduling. (search for similar items in EconPapers)
Date: 2014
References: Add references at CitEc
Citations:
Downloads: (external link)
http://www.inderscience.com/link.php?id=59744 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:ids:ijpoma:v:6:y:2014:i:1/2:p:48-66
Access Statistics for this article
More articles in International Journal of Project Organisation and Management from Inderscience Enterprises Ltd
Bibliographic data for series maintained by Sarah Parker ().