The Use of Management Science to Support a Multimillion Dollar Precedent-Setting Government Contract Litigation

Steven Nahmias
Additional contact information
Steven Nahmias: Department of Industrial Engineering, University of Pittsburgh, 1048 Benedum Hall, Pittsburgh, Pennsylvania, 15261

Interfaces, 1980, vol. 10, issue 1, 1-12

Abstract: This paper describes the analysis of relevant data presented by this writer at a hearing conducted before the Armed Services Board of Contract Appeals involving an appeal of the Ingalls Shipbuilding Division of Litton Industries. The appeal concerned contracts awarded to Litton by the U.S. Navy to build four nuclear submarines and the subsequent impact of changes and delays to these contracts on other shipyard operations. Behind this appeal is the fundamental question of whether or not the government is required to assume liability and reimburse the contractor for additional costs incurred due to “ripple effects” of contract changes on other shipyard operations.

Keywords: statistics: pattern analysis; judicial/legal (search for similar items in EconPapers)
Date: 1980
References: Add references at CitEc
Citations: View citations in EconPapers (2)

Downloads: (external link)
http://dx.doi.org/10.1287/inte.10.1.1 (application/pdf)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:inm:orinte:v:10:y:1980:i:1:p:1-12

Access Statistics for this article

More articles in Interfaces from INFORMS Contact information at EDIRC.
Bibliographic data for series maintained by Chris Asher ().

 
Page updated 2025-03-19
Handle: RePEc:inm:orinte:v:10:y:1980:i:1:p:1-12