Due Date-Based Metrics for Activity Importance in Stochastic Activity Networks

R.A. Bowman

Annals of Operations Research, 2001, vol. 102, issue 1, 39-48

Abstract: A metric pair for assessing the importance of activities in stochastic activity networks based on completing a project on time (or reaching other project milestones) is presented. The metric pair is recommended as a supplement to other metrics of activity importance that have been suggested for use with Monte Carlo simulation. The differences in behavior of the various metrics are analyzed to help understand the additional types of insights that would be available by including the new metrics in simulation-based analyses. Copyright Kluwer Academic Publishers 2001

Keywords: PERT; project management; stochastic activity networks; activity criticality; conditional estimators; Monte Carlo simulation (search for similar items in EconPapers)
Date: 2001
References: Add references at CitEc
Citations: View citations in EconPapers (2)

Downloads: (external link)
http://hdl.handle.net/10.1023/A:1010993713274 (text/html)
Access to full text is restricted to subscribers.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:spr:annopr:v:102:y:2001:i:1:p:39-48:10.1023/a:1010993713274

Ordering information: This journal article can be ordered from
http://www.springer.com/journal/10479

DOI: 10.1023/A:1010993713274

Access Statistics for this article

Annals of Operations Research is currently edited by Endre Boros

More articles in Annals of Operations Research from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().

 
Page updated 2025-03-20
Handle: RePEc:spr:annopr:v:102:y:2001:i:1:p:39-48:10.1023/a:1010993713274