Joint optimization of production scheduling and group preventive maintenance planning in multi-machine systems

Aseem K. Mishra (), Divya Shrivastava (), Devesh Tarasia () and Abdur Rahim ()
Additional contact information
Aseem K. Mishra: Birla Institute of Management Technology
Divya Shrivastava: Shiv Nadar University
Devesh Tarasia: Northeastern University
Abdur Rahim: University of New Brunswick

Annals of Operations Research, 2022, vol. 316, issue 1, No 15, 444 pages

Abstract: Abstract This paper addresses the joint optimization model of production scheduling, work-in-process (WIP) inventory control and group preventive maintenance (PM) planning in a multi-machine system with multi-components. The objective is to obtain optimum production sequence, PM intervals and grouping of components, which minimize the total expected cost per unit time of the system. A new meta-heuristic named Jaya algorithm and two popular algorithms viz. simulated annealing (SA) and particle swarm optimization (PSO) are applied to optimize the objective function. Initially, the optimum group of components is obtained based on the integer multiples of individual PM intervals. Secondly, the job permutation sequence incorporating group PM intervals is identified with the largest order value (LOV) rule. The shift in optimum PM intervals is realized with an advanced-postpone balancing approach. Computational results reveal that the proposed integrated model along with group PM yields up to 25% cost reductions when compared to the integrated model with individual maintenance as well as 37% savings while no integration is performed. Furthermore, the performance of algorithms is evaluated with large-sized problems. The obtained results show that Jaya and SA yielded comparable results, however, PSO is least productive. Thus, the proposed approach yields better economic performance and brings more improvised solutions as compared to the conventional methods of integrated scheduling and maintenance optimization problems.

Keywords: Production scheduling; Group maintenance; Integration; Multi-machine multi-component system; Jaya algorithm (search for similar items in EconPapers)
Date: 2022
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (1)

Downloads: (external link)
http://link.springer.com/10.1007/s10479-021-04362-z Abstract (text/html)
Access to the full text of the articles in this series is restricted.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:spr:annopr:v:316:y:2022:i:1:d:10.1007_s10479-021-04362-z

Ordering information: This journal article can be ordered from
http://www.springer.com/journal/10479

DOI: 10.1007/s10479-021-04362-z

Access Statistics for this article

Annals of Operations Research is currently edited by Endre Boros

More articles in Annals of Operations Research from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().

 
Page updated 2025-03-20
Handle: RePEc:spr:annopr:v:316:y:2022:i:1:d:10.1007_s10479-021-04362-z