A robust multi-project scheduling problem under a resource dedication-transfer policy

Yan Zhao, Xuejun Hu (), Jianjiang Wang and Nanfang Cui
Additional contact information
Yan Zhao: Zhongnan University of Economics and Law
Xuejun Hu: Hunan University
Jianjiang Wang: National University of Defense Technology
Nanfang Cui: Huazhong University of Science and Technology

Annals of Operations Research, 2024, vol. 337, issue 1, No 14, 425-457

Abstract: Abstract In multi-project management, effectively allocating limited resources to projects is crucial for ensuring the success of the project portfolio and timely delivery. There are two approaches to managing renewable resources based on project execution environment and resource characteristics: resource sharing and resource dedication. This study explores a novel resource dedication-transfer policy, where renewable resources are dedicated to each project during execution and can be transferred to other projects once the corresponding project is completed. Additionally, real-world multi-project scheduling often faces uncertainties, with the most common issue being varying durations of activities. To address this, a hierarchical multi-objective optimization model is proposed under the resource dedication-transfer policy. This model aims to allocate dedicated resources to the project portfolio at a tactical level and schedule individual activities at an operational level. The specific objectives include minimizing the total weighted tardiness of all projects, minimizing the total fluctuating costs of resources, and maximizing solution robustness in the presence of activity duration variabilities. The proposed solution methodologies include an adjusted large neighborhood search (ALNS) and a customized NSGA-II algorithm. Both algorithms employ a hybrid coding scheme of “project-buffer-resource-activity” list to represent feasible solutions. Specially, the ALNS introduces new destroy-repair neighborhood operators and a hypervolume-based selection criterion to enhance its performance. Experimental results demonstrate that while both algorithms have their advantages for small-scale instances, the ALNS is more effective for large-scale instances. Finally, the derived Pareto solutions from the proposed method are further evaluated through a simulation of multi-project execution under different levels of activity duration variabilities.

Keywords: Multi-project scheduling; Resource dedication; Resource transfer; Duration uncertainties; Multi-objective optimization; Adjusted large neighborhood search (search for similar items in EconPapers)
Date: 2024
References: View references in EconPapers View complete reference list from CitEc
Citations:

Downloads: (external link)
http://link.springer.com/10.1007/s10479-024-05854-4 Abstract (text/html)
Access to the full text of the articles in this series is restricted.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:spr:annopr:v:337:y:2024:i:1:d:10.1007_s10479-024-05854-4

Ordering information: This journal article can be ordered from
http://www.springer.com/journal/10479

DOI: 10.1007/s10479-024-05854-4

Access Statistics for this article

Annals of Operations Research is currently edited by Endre Boros

More articles in Annals of Operations Research from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().

 
Page updated 2025-04-20
Handle: RePEc:spr:annopr:v:337:y:2024:i:1:d:10.1007_s10479-024-05854-4