A new proactive and reactive approach for resource-constrained project scheduling problem under activity and resource disruption: a scenario-based robust optimization approach
Maziar Khoshsirat () and
Seyed Meysam Mousavi ()
Additional contact information
Maziar Khoshsirat: Shahed University
Seyed Meysam Mousavi: Shahed University
Annals of Operations Research, 2024, vol. 338, issue 1, No 22, 597-643
Abstract:
Abstract This paper introduces a novel two-phase framework for designing a proactive–reactive scheduling model in the multi-mode resource-constrained project scheduling problem under disruptions. The proactive phase involves constructing a resilient baseline scheduling model using a mixed-integer linear programming model. This phase contributes to a multi-objective model that minimizes the project completion time and total project cost while maximizing resilience criteria. In this context, resilience refers to allocating float time to project activities to protect their start and finish times against future disruptions as much as possible. The reactive phase involves a bi-objective mathematical model that mitigates the impact of disruptions through preempt-repeat, preempt-resume, and activity-crashing strategies. Real-world projects involve many uncertain parameters that can negatively affect the optimization of rescheduling problems if overlooked. Therefore, for the first time, a scenario-based robust optimization approach is proposed to cope with the uncertainty of the reactive phase. Additionally, a novel hybrid multi-objective method based on goal programming is introduced to solve the proposed multi-objective model. Finally, to demonstrate the capability of the proposed approach, an oil and gas project in Iran is regarded as a real case study. The results indicate that the negative impact of disruptions on the makespan and total cost of the project can be largely mitigated by considering resilience criteria in the proactive phase and preempt-repeat, preempt-resume, and activity-crashing strategies in the reactive phase.
Keywords: Multi-mode resource-constrained project scheduling; Disruption; Resiliency; Proactive and reactive scheduling; Scenario-based robust optimization; Hybrid multi-objective method (search for similar items in EconPapers)
Date: 2024
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
http://link.springer.com/10.1007/s10479-024-05895-9 Abstract (text/html)
Access to the full text of the articles in this series is restricted.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:spr:annopr:v:338:y:2024:i:1:d:10.1007_s10479-024-05895-9
Ordering information: This journal article can be ordered from
http://www.springer.com/journal/10479
DOI: 10.1007/s10479-024-05895-9
Access Statistics for this article
Annals of Operations Research is currently edited by Endre Boros
More articles in Annals of Operations Research from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().