Defining accurate delivery dates in make to order job-shops managed by workload control
Davide Mezzogori,
Giovanni Romagnoli and
Francesco Zammori ()
Additional contact information
Davide Mezzogori: University of Parma
Giovanni Romagnoli: University of Parma
Francesco Zammori: University of Parma
Flexible Services and Manufacturing Journal, 2021, vol. 33, issue 4, No 3, 956-991
Abstract:
Abstract Workload control (WLC) is a lean oriented system that reduces queues and waiting times, by imposing a cap to the workload released to the shop floor. Unfortunately, WLC performance does not systematically outperform that of push operating systems, with undersaturated utilizations levels and optimized dispatching rules. To address this issue, many scientific works made use of complex job-release mechanisms and sophisticated dispatching rules, but this makes WLC too complicated for industrial applications. So, in this study, we propose a complementary approach. At first, to reduce queuing time variability, we introduce a simple WLC system; next we integrate it with a predictive tool that, based on the system state, can accurately forecast the total time needed to manufacture and deliver a job. Due to the non-linearity among dependent and independent variables, forecasts are made using a multi-layer-perceptron; yet, to have a comparison, the effectiveness of both linear and non-linear multi regression model has been tested too. Anyhow, if due dates are endogenous (i.e. set by the manufacturer), they can be directly bound to this internal estimate. Conversely, if they are exogenous (i.e. set by the customer), this approach may not be enough to minimize the percentage of tardy jobs. So, we also propose a negotiation scheme, which can be used to extend exogenous due dates considered too tight, with respect to the internal estimate. This is the main contribution of the paper, as it makes the forecasting approach truly useful in many industrial applications. To test our approach, we simulated a 6-machines job-shop controlled with WLC and equipped with the proposed forecasting system. Obtained performances, namely WIP levels, percentage of tardy jobs and negotiated due dates, were compared with those of a set classical benchmark, and demonstrated the robustness and the quality of our approach, which ensures minimal delays.
Keywords: Delivery dates; Discrete event simulation; Job-shop; Workload control; Regression; Neural network (search for similar items in EconPapers)
Date: 2021
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (4)
Downloads: (external link)
http://link.springer.com/10.1007/s10696-020-09396-2 Abstract (text/html)
Access to the full text of the articles in this series is restricted.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:spr:flsman:v:33:y:2021:i:4:d:10.1007_s10696-020-09396-2
Ordering information: This journal article can be ordered from
http://www.springer.com/journal/10696
DOI: 10.1007/s10696-020-09396-2
Access Statistics for this article
Flexible Services and Manufacturing Journal is currently edited by Hans Günther
More articles in Flexible Services and Manufacturing Journal from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().