A genetic-algorithm-based resource-constrained construction scheduling system
Sou-Sen Leu and
Chung-Huei Yang
Construction Management and Economics, 1999, vol. 17, issue 6, 767-776
Abstract:
Resources for construction activities are limited in the real construction world. To avoid waste and shortage of resources on a construction jobsite, scheduling must include resource allocation. A new resourceconstrained construction scheduling system is proposed in this paper. A GA-based searching technique is adopted in the system. In this paper, new GA crossover and mutation operators, UX3 and UM3, are presented. These new operators overcome the drawback of traditional GA operators for sequencing problems. The system effectively can provide the optimal combination of construction duration, resource quantities and minimum project duration under the constraint of limited resources.
Keywords: Resource Constraint; Genetic Algorithms; Scheduling; Resource Allocation; Multiple-objective; Programming (search for similar items in EconPapers)
Date: 1999
References: View complete reference list from CitEc
Citations: View citations in EconPapers (6)
Downloads: (external link)
http://www.tandfonline.com/doi/abs/10.1080/014461999371105 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:taf:conmgt:v:17:y:1999:i:6:p:767-776
Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/RCME20
DOI: 10.1080/014461999371105
Access Statistics for this article
Construction Management and Economics is currently edited by Will Hughes
More articles in Construction Management and Economics from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().