Flowshop scheduling model for bespoke precast concrete production planning
Vacharapoom Benjaoran,
Nashwan Dawood and
Brian Hobbs
Construction Management and Economics, 2005, vol. 23, issue 1, 93-105
Abstract:
Bespoke precast concrete products are particularly designed and custom made for a construction project. The production planning of these products is complicated that considers important concerns, i.e. the reliability of the product delivery programme, the short lead-time competitiveness, and the effective utilization of purpose-built precast moulds. The planning has a high impact on the success of the production. The characteristics of the bespoke precast production are formulated with the flowshop scheduling technique so that an effective production plan can be arranged to meet these concerns. Genetic algorithm is used in the scheduling optimization. Its multi-objective function includes total flowtime, total machine idle time, and total tardiness and earliness. After the model formulation, sensitivity analyses are conducted on the three model's parameters namely the number of mould availability, the processing time changes, and the weighting of the multi-objective function. The proposed model is anticipated to support the planners to arrange economic and efficient production plans. Also, it can be used to determine the suitable number of moulds, the accuracy of the processing time estimation, and the weighting strategy of the multi-objective optimization.
Keywords: flowshop scheduling; bespoke precast concrete; production planning; genetic algorithm (search for similar items in EconPapers)
Date: 2005
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (2)
Downloads: (external link)
http://www.tandfonline.com/doi/abs/10.1080/0144619042000287732 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:taf:conmgt:v:23:y:2005:i:1:p:93-105
Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/RCME20
DOI: 10.1080/0144619042000287732
Access Statistics for this article
Construction Management and Economics is currently edited by Will Hughes
More articles in Construction Management and Economics from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().