Productivity and delays assessment for concrete batch plant-truck mixer operations

Tarek Zayed, Daniel Halpin and Ismail Basha

Construction Management and Economics, 2005, vol. 23, issue 8, 839-850

Abstract: Current research focuses on assessing productivity, cost, and delays for concrete batch plant (CBP) operations using Artificial Neural Network (ANN) methodology. Data were collected to assess cycle time, delays, cost of delays, cost of delivery, productivity, and price/m3 for the CBP. Two ANN models were designated to represent the CBP process considering many CBP variables. Input variables include delivery distance, concrete type, and truck mixer's load. Output variables include the assessment of cycle time, cost of delays, delivery cost, productivity, and price/m3. The ANN outputs have been validated to show the ANN's robustness in assessing the CBP output variables. The average validity percent for the ANN outputs is 96.25%. A Time-Quantity (TQ) chart is developed to assess the time required for both truck mixers and the CBP to produce a specified quantity of concrete. Charts have been developed to predict cycle time/truck, delays/truck, cost of delays/truck, cost of delivery/m3, and price/m3.

Keywords: Artificial Neural Network (ANN); productivity; cost analysis; cycle time; modeling; concrete batch plant (CBP); truck mixer (search for similar items in EconPapers)
Date: 2005
References: View complete reference list from CitEc
Citations:

Downloads: (external link)
http://www.tandfonline.com/doi/abs/10.1080/01446190500184451 (text/html)
Access to full text is restricted to subscribers.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:taf:conmgt:v:23:y:2005:i:8:p:839-850

Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/RCME20

DOI: 10.1080/01446190500184451

Access Statistics for this article

Construction Management and Economics is currently edited by Will Hughes

More articles in Construction Management and Economics from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().

 
Page updated 2025-03-20
Handle: RePEc:taf:conmgt:v:23:y:2005:i:8:p:839-850