Automated trade-off between time and cost in planning repetitive construction projects
Khalied Hesham Hyari,
Khaled El-Rayes and
Mohammad El-Mashaleh
Construction Management and Economics, 2009, vol. 27, issue 8, 749-761
Abstract:
An automated model is developed to support the optimization of the planning and scheduling of repetitive construction projects. The model provides the capability of optimizing two important objectives commonly sought in scheduling repetitive construction projects: minimizing project duration; and minimizing project cost. The model performs this multi-objective optimization using a genetic algorithm approach. The output of the model is a set of optimal solutions that represent the trade-off between time and cost in planning repetitive construction projects. Furthermore, the model can be utilized to find a single scheduling solution that provides the minimum overall project cost by simply adding project indirect cost to the obtained project direct cost for each of the obtained scheduling solutions on the Pareto optimal curve. Other important time-related costs are also considered in the model including: early completion incentives, late completion penalties and lane rental costs. Providing the planners of repetitive construction projects with an automated set of optimal time-cost trade-off solutions should contribute to cost-effective and speedy delivery of this type of construction project. An application example is analysed to illustrate the use of the model and demonstrate its capabilities in generating optimal trade-off solutions between minimizing the project time and cost for repetitive construction projects.
Keywords: Repetitive construction; scheduling; genetic algorithms; optimization; resource utilization (search for similar items in EconPapers)
Date: 2009
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
http://www.tandfonline.com/doi/abs/10.1080/01446190903117793 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:taf:conmgt:v:27:y:2009:i:8:p:749-761
Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/RCME20
DOI: 10.1080/01446190903117793
Access Statistics for this article
Construction Management and Economics is currently edited by Will Hughes
More articles in Construction Management and Economics from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().