Safety risk interactions among highway construction work tasks

Matthew Hallowell, Behzad Esmaeili and Paul Chinowsky

Construction Management and Economics, 2011, vol. 29, issue 4, 417-429

Abstract: Recent research has produced frameworks for integrating safety risk data into project schedules, visual models and other construction planning tools. Unfortunately, only a few studies have attempted to quantify base-level safety risk for construction tasks and no study has attempted to quantify the degree to which spatial and temporal interactions among tasks contribute to the potential for injury. A research study was performed to quantify the impact that pair-wise spatial and temporal interactions have on the base-level risk of 25 common highway construction work tasks in the United States. Six hundred risk interactions were quantified by obtaining and aggregating over 23 500 individual ratings from certified experts using the Delphi method. The results indicate that incompatible tasks may increase the base-level risk up to 60%. The most incompatible highway construction tasks are: (1) installing curbs and gutters and installing rigid pavement; and (2) construction zone traffic control and installing rigid pavement. Additionally, watering and dust palliatives and pavement marking is the one compatible task pair and there are 45 neutral task pairs. The resulting database and analysis have the potential to increase the efficacy of existing frameworks for integration of safety risk data with project planning tools.

Keywords: Project management; risk analysis; safety (search for similar items in EconPapers)
Date: 2011
References: View complete reference list from CitEc
Citations: View citations in EconPapers (3)

Downloads: (external link)
http://www.tandfonline.com/doi/abs/10.1080/01446193.2011.552512 (text/html)
Access to full text is restricted to subscribers.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:taf:conmgt:v:29:y:2011:i:4:p:417-429

Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/RCME20

DOI: 10.1080/01446193.2011.552512

Access Statistics for this article

Construction Management and Economics is currently edited by Will Hughes

More articles in Construction Management and Economics from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().

 
Page updated 2025-03-20
Handle: RePEc:taf:conmgt:v:29:y:2011:i:4:p:417-429