How can 'tasks made ready' during lookahead planning impact reliable workflow and project duration?

Farook R. Hamzeh, Emile Zankoul and Carel Rouhana

Construction Management and Economics, 2015, vol. 33, issue 4, 243-258

Abstract: The goal of lookahead planning is to make a plan more realistic as construction tasks move closer to execution. To improve the reliability of lookahead planning, the construction industry has benefited from implementing the Last Planner-super-® System (LPS) which emphasizes improved workflow during construction. Lookahead planning involves transforming work that 'should be done' into work that 'can be done'. This is accomplished by breaking down activities into the level of operations, designing operations, and making tasks ready by removing task constraints. The purpose of this research is to study, through computer simulation, the relationship between improving tasks made ready (TMR) in lookahead planning and the reliability of weekly work planning expressed as percent plan complete (PPC) and their impact on project duration. Results show that a high TMR can result in a reduced project duration but the same cannot be said about PPC, making a case for TMR serving as a better indicator for project duration than PPC.

Date: 2015
References: View complete reference list from CitEc
Citations: View citations in EconPapers (1)

Downloads: (external link)
http://hdl.handle.net/10.1080/01446193.2015.1047878 (text/html)
Access to full text is restricted to subscribers.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:taf:conmgt:v:33:y:2015:i:4:p:243-258

Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/RCME20

DOI: 10.1080/01446193.2015.1047878

Access Statistics for this article

Construction Management and Economics is currently edited by Will Hughes

More articles in Construction Management and Economics from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().

 
Page updated 2025-03-20
Handle: RePEc:taf:conmgt:v:33:y:2015:i:4:p:243-258