Scheduling on a proportionate flowshop to minimise total late work
Enrique Gerstl,
Baruch Mor and
Gur Mosheiov
International Journal of Production Research, 2019, vol. 57, issue 2, 531-543
Abstract:
We study a scheduling problem to minimise total late work, i.e. each job is penalised according to the duration of its parts scheduled after its due-date. The machine setting is an m-machine proportionate flow shop. Two versions of the problem are studied: (i) the case that total late work refers to the last operation of the job (i.e. the operation performed on the last machine of the flow shop); (ii) the case that total late work refers to all the operations (on all machines). Both versions are known to be NP-hard. We prove a crucial property of an optimal schedule, and consequently introduce efficient pseudo-polynomial dynamic programming algorithms for the two versions. The dynamic programming algorithms are tested numerically and proved to perform well on large size instances.
Date: 2019
References: Add references at CitEc
Citations: View citations in EconPapers (10)
Downloads: (external link)
http://hdl.handle.net/10.1080/00207543.2018.1456693 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:taf:tprsxx:v:57:y:2019:i:2:p:531-543
Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/TPRS20
DOI: 10.1080/00207543.2018.1456693
Access Statistics for this article
International Journal of Production Research is currently edited by Professor A. Dolgui
More articles in International Journal of Production Research from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().