Convex resource allocation scheduling in the no-wait flowshop with common flow allowance and learning effect
Xinyu Sun,
Xin-Na Geng,
Ji-Bo Wang and
Feng Liu
International Journal of Production Research, 2019, vol. 57, issue 6, 1873-1891
Abstract:
We study the problem of two-machine no-wait flowshop scheduling with learning effect and convex resource-dependent processing times. Under the condition of the due-date assignment with common flow allowance (i.e. slack (SLK) due-date assignment), we provide a bi-criteria analysis where the first criterion is to minimise the scheduling criteria (i.e. the weighted sum of earliness, tardiness and flow allowance costs), and the second criterion is to minimise the resource consumption cost (i.e. the weighted sum of resource consumption cost). The objective is to determine the optimal job sequence, resource allocations and common (flow allowance) slack time that minimise the three different versions of the two criteria. We prove that these problems can be solved in polynomial time.
Date: 2019
References: Add references at CitEc
Citations: View citations in EconPapers (3)
Downloads: (external link)
http://hdl.handle.net/10.1080/00207543.2018.1510559 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:taf:tprsxx:v:57:y:2019:i:6:p:1873-1891
Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/TPRS20
DOI: 10.1080/00207543.2018.1510559
Access Statistics for this article
International Journal of Production Research is currently edited by Professor A. Dolgui
More articles in International Journal of Production Research from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().