A joint work package sizing and scheduling problem considering resource constraints with a look-ahead heterogeneous reinforcement learning method
Nianmin Zhang,
Xiao Li and
Yao Gao
International Journal of Production Research, 2025, vol. 63, issue 10, 3760-3797
Abstract:
Effective work package sizing and project scheduling are crucial for construction project management. However, existing studies often address them as separate optimisation problems, neglecting the interactive nature of these processes. In practical scenarios with limited resources, there is an increasing demand for integrating work package sizing and project scheduling to enhance project management efficiency. This research aims to bridge this gap by developing an integer non-linear programming model that incorporates work package sizing and project scheduling while considering their interaction within a resource-constrained environment. Moreover, we introduce a novel look-ahead heterogeneous reinforcement learning approach that dynamically adjusts work package sizes and project schedules based on observed information at each decision step. A look-ahead sequential decision mechanism is proposed to effectively address the interdependencies and constraints inherent in the joint model. We extend the heterogeneous agent mirror learning technique to our problem to improve sample efficiency and ensure progressive enhancement of the joint policy. To evaluate our approach's effectiveness, we conduct experiments using datasets of 15, 30, 60, 90, and 120 tasks from Rangen and PSPLIB and validate our method in a real-world modular integrated construction project. The experimental results reveal that a joint model integrating work package sizing and project scheduling offers a more comprehensive understanding of their interplay, leading to better resource utilisation and improved project schedules. A comparative analysis against existing state-of-the-art reinforcement learning and priority rule-based methods further substantiates the superior effectiveness of our proposed approach, yielding an approximate 5% reduction in total project cost.
Date: 2025
References: Add references at CitEc
Citations:
Downloads: (external link)
http://hdl.handle.net/10.1080/00207543.2024.2430457 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:taf:tprsxx:v:63:y:2025:i:10:p:3760-3797
Ordering information: This journal article can be ordered from
http://www.tandfonline.com/pricing/journal/TPRS20
DOI: 10.1080/00207543.2024.2430457
Access Statistics for this article
International Journal of Production Research is currently edited by Professor A. Dolgui
More articles in International Journal of Production Research from Taylor & Francis Journals
Bibliographic data for series maintained by Chris Longhurst ().