Shuffled Frog Leaping Algorithm for Preemptive Project Scheduling Problems with Resource Vacations Based on Patterson Set
Yi Han,
Ikou Kaku,
Jianhu Cai,
Yanlai Li,
Chao Yang and
Lili Deng
Journal of Applied Mathematics, 2013, vol. 2013, issue 1
Abstract:
This paper presents a shuffled frog leaping algorithm (SFLA) for the single‐mode resource‐constrained project scheduling problem where activities can be divided into equant units and interrupted during processing. Each activity consumes 0–3 types of resources which are renewable and temporarily not available due to resource vacations in each period. The presence of scarce resources and precedence relations between activities makes project scheduling a difficult and important task in project management. A recent popular metaheuristic shuffled frog leaping algorithm, which is enlightened by the predatory habit of frog group in a small pond, is adopted to investigate the project makespan improvement on Patterson benchmark sets which is composed of different small and medium size projects. Computational results demonstrate the effectiveness and efficiency of SFLA in reducing project makespan and minimizing activity splitting number within an average CPU runtime, 0.521 second. This paper exposes all the scheduling sequences for each project and shows that of the 23 best known solutions have been improved.
Date: 2013
References: Add references at CitEc
Citations:
Downloads: (external link)
https://doi.org/10.1155/2013/451090
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:wly:jnljam:v:2013:y:2013:i:1:n:451090
Access Statistics for this article
More articles in Journal of Applied Mathematics from John Wiley & Sons
Bibliographic data for series maintained by Wiley Content Delivery ().