Minimal forecast horizons in equipment replacement models with multiple technologies and general switching costs
S. Bylka,
Suresh Sethi and
Gerhard Sorger
Naval Research Logistics (NRL), 1992, vol. 39, issue 4, 487-507
Abstract:
This article considers the problem of equipment replacement in which the replacement decision at a particular time must take into account (i) the state of the existing machine in use, (ii) the available replacement alternatives at the time, (iii) the future advances in the relevant technologies with regard to the equipment under consideration, and (iv) costs of switching between different technologies. A methodology that attains minimal forecast horizons for the problem is developed. A numerical example illustrates the methodology.
Date: 1992
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (8)
Downloads: (external link)
https://doi.org/10.1002/1520-6750(199206)39:43.0.CO;2-6
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:wly:navres:v:39:y:1992:i:4:p:487-507
Access Statistics for this article
More articles in Naval Research Logistics (NRL) from John Wiley & Sons
Bibliographic data for series maintained by Wiley Content Delivery ().