Multidirectional scheduling scheme in resource‐constrained project schedulingproblem
Hamid R. Yoosefzadeh,
Hamed R. Tareghian and
Mohammad H. Farahi
Naval Research Logistics (NRL), 2014, vol. 61, issue 1, 44-55
Abstract:
In 2000, Klein showed that bidirectional scheduling schemes (bidss) outperform single‐directional scheduling schemes (e.g., forward or backward schemes). In 2010, Yoosefzadeh, et al. [J Math Model Algor 9 (2010), 357–373] showed that depending on the nature of the problems and also the type of priority rules used, schedules produced by a so‐called tridirectional scheduling scheme (trdss) yields shorter makespans when compared to forward, backward, and even bidss. Since the justification technique is applied in many of the state‐of‐the‐art algorithms nowadays, we show that the tuned version of the trdss outperforms the double justification technique. Moreover, we investigate the circumstances under which the trdss is more probable to generate schedules with shorter makespans. To this end, we introduce a new measure of resource requirements and their distributions, namely total amount of overflows. Our analytical as well as empirical investigations show that when the new measure is increased, it is more probable to obtain schedules with shorter makespans using the trdss. © 2013 Wiley Periodicals, Inc. Naval Research Logistics 61: 44–55, 2014
Date: 2014
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
https://doi.org/10.1002/nav.21565
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:wly:navres:v:61:y:2014:i:1:p:44-55
Access Statistics for this article
More articles in Naval Research Logistics (NRL) from John Wiley & Sons
Bibliographic data for series maintained by Wiley Content Delivery ().