Hot Strip Mill Scheduling Under Consideration of Energy Consumption
Karen Puttkammer (),
Matthias G. Wichmann () and
Thomas S. Spengler ()
Additional contact information
Karen Puttkammer: Technische Universität Braunschweig
Matthias G. Wichmann: Technische Universität Braunschweig
Thomas S. Spengler: Technische Universität Braunschweig
A chapter in Operations Research Proceedings 2013, 2014, pp 355-361 from Springer
Abstract:
Abstract In steel industry hot rolling is an energy-intensive process as steel slabs need to be heated to about 1,250 $$^\circ $$ ∘ C before being rolled on the hot strip mill. Due to time-dependent piecewise energy demand, the total energy consumption for heating is determined by the hot rolling schedule. However, there is no modeling approach known which incorporates the interdependencies between the schedule, the charging time of the slabs, their charging temperature and the energy requirement for heating. We present a MILP formulation for the hot strip mill scheduling problem (HSMSP) under consideration of energy consumption. It takes into account the mentioned interdependencies as well as setups and makespan.
Keywords: Setup Time; Total Energy Consumption; Setup Cost; Width Profile; Adjacent Order (search for similar items in EconPapers)
Date: 2014
References: Add references at CitEc
Citations:
There are no downloads for this item, see the EconPapers FAQ for hints about obtaining it.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:spr:oprchp:978-3-319-07001-8_48
Ordering information: This item can be ordered from
http://www.springer.com/9783319070018
DOI: 10.1007/978-3-319-07001-8_48
Access Statistics for this chapter
More chapters in Operations Research Proceedings from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().