Project Scheduling with Precedence Constraints and Scarce Resources: An Experimental Analysis of Commercial Project Management Software
Norbert Trautmann () and
Philipp Baumann ()
Additional contact information
Norbert Trautmann: Universität Bern, Departement Betriebswirtschaftslehre, AP Quantitative Methoden
Philipp Baumann: Universität Bern, Departement Betriebswirtschaftslehre, AP Quantitative Methoden
Chapter 27 in Operations Research Proceedings 2008, 2009, pp 165-170 from Springer
Abstract:
Summary We report on the results of an experimental analysis where we have compared the resource allocation capabilities of recent versions of 5 commercial project management software packages against state-of-the-art solution methods from the literature. For our analysis, we have used 1560 RCPSP instances from the standard test set PSPLIB. The results indicate that using the automatic resource allocating feature of those packages may result in project durations that are considerably longer than necessary, in particular when the resource scarcity is high or when the number of activities is large.
Keywords: Resource Allocation; Project Schedule; Resource Capacity; Precedence Relationship; Project Schedule Problem (search for similar items in EconPapers)
Date: 2009
References: Add references at CitEc
Citations:
There are no downloads for this item, see the EconPapers FAQ for hints about obtaining it.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:spr:sprchp:978-3-642-00142-0_27
Ordering information: This item can be ordered from
http://www.springer.com/9783642001420
DOI: 10.1007/978-3-642-00142-0_27
Access Statistics for this chapter
More chapters in Springer Books from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().