An Improved NSGA-II Algorithm for Resource-Constrained Discrete Time–Cost Tradeoff Problem

Hong Zha () and Lian-ying Zhang
Additional contact information
Hong Zha: Tianjin University
Lian-ying Zhang: Tianjin University

Chapter Chapter 18 in The 19th International Conference on Industrial Engineering and Engineering Management, 2013, pp 159-166 from Springer

Abstract: Abstract In this paper, a resource-constrained discrete time and cost tradeoff problem (RCDTCTP) is considered in knowledge intensive project, where the resources are mainly renewable resource, especially manpower. A multi-objective model for this problem is proposed. In order to illustrate the model, an improved non-dominated sorting genetic algorithm is introduced to solve the model with a numerical example. The results showed that a set of Pareto optimal scheduling alternatives can be obtained in given resource constraints, from which the project stakeholder can choose the preferred alternative.

Keywords: Improved NSGA-II; Multi-objective; Project scheduling; Time–cost tradeoff (search for similar items in EconPapers)
Date: 2013
References: Add references at CitEc
Citations:

There are no downloads for this item, see the EconPapers FAQ for hints about obtaining it.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:spr:sprchp:978-3-642-38433-2_18

Ordering information: This item can be ordered from
http://www.springer.com/9783642384332

DOI: 10.1007/978-3-642-38433-2_18

Access Statistics for this chapter

More chapters in Springer Books from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().

 
Page updated 2025-03-23
Handle: RePEc:spr:sprchp:978-3-642-38433-2_18