Optimization on Earned Value Method Combined with Critical Path

Qi-bin Zheng () and Xing Bi
Additional contact information
Qi-bin Zheng: Tianjin University
Xing Bi: Tianjin University

A chapter in Proceedings of 2013 4th International Asia Conference on Industrial Engineering and Management Innovation (IEMI2013), 2014, pp 707-715 from Springer

Abstract: Abstract When calculating the schedule performance using the traditional earned value method, the earned value in the critical path and in the noncritical path is not differentiated. It cannot evaluate the progress of project objectively. In this paper, the schedule performance indicators are optimized through introducing the weight value, and schedule performance on the critical path is analyzed. The critical path issues in the evaluation of the progress of the project are solved, which will provide a basic point of reference for schedule measurement of project.

Keywords: Critical path; Earned value method; Optimization; Weight value (search for similar items in EconPapers)
Date: 2014
References: Add references at CitEc
Citations:

There are no downloads for this item, see the EconPapers FAQ for hints about obtaining it.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:spr:sprchp:978-3-642-40060-5_68

Ordering information: This item can be ordered from
http://www.springer.com/9783642400605

DOI: 10.1007/978-3-642-40060-5_68

Access Statistics for this chapter

More chapters in Springer Books from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().

 
Page updated 2025-03-23
Handle: RePEc:spr:sprchp:978-3-642-40060-5_68