Interconnector Investment for a Well-functioning Internal Market. What EU regime of regulatory incentives?
Jacques Pelkmans and
Lionel Kapff
Additional contact information
Jacques Pelkmans: Senior Research Fellow, CEPS (Brussels); Visiting Professor, College of Europe (Bruges)
No 18, Bruges European Economic Research Papers from European Economic Studies Department, College of Europe
Abstract:
Sufficient cross-border electricity transmission infrastructure is a pre-requisite for a functioning European internal market for electricity. Also, the achievement of the EU’s energy policy objectives – sustainability, competitiveness and security of supply – critically depends on adequate investment in physical interconnections between the member states. Mainly focusing on the “regulatory path”, this paper assesses different ways to achieve a sufficient level of interconnector investment. In a first step, economic analysis identifies numerous impediments to interconnector investment adding up to an “interconnector investment failure”. Reflecting on the proper regulatory design of an EU framework able to overcome the interconnector investment failure, a number of recommendations are put forward: - All congestion rents should be channeled into interconnector building. Unused rents should be transferred to a European interconnector fund supervised by an EU agency. - Even though inherently sub-optimal, merchant transmission investment can be used as a means to put pressure on regulated transmission system operators (TSO) that do not deliver. An EU agency should have exclusive competence on merchant interconnector exemptions. - A European TSO organization should be entrusted with supra-national network planning, supervised by an EU agency. - The agency should decide on investment cost reallocation for interconnector projects that yield strong externalities. Payments could be settled via a European interconnector fund. - In case of non-compliance with the supra-national network plan, the EU agency should have the right to organize a tender – financed by the European interconnector fund – in order to get the “missing link” built. Assessing the existing EU regulatory framework, the efforts of the 2009 “third energy package” to fill the “regulatory gap” with new EU bodies – ACER and ENTSO-E – are acknowledged. However, striking holes in regulatory framework are spotted, notably with regard to the use of congestion rents, interconnector cost allocation, and the distribution of decision making powers on new infrastructure exemptions A discussion of the TEN-E interconnector funding scheme shows that massive funding can be an interim solution to the problem of insufficient interconnection capacities while overcoming the political deadlock on sensible regulatory topics such as interconnector cost allocation. The paper ends with policy recommendations.
Keywords: cross-border electricity transmission infrastructure; interconnection; internal electricity market; investment incentives; third energy package (search for similar items in EconPapers)
JEL-codes: F15 L51 L94 (search for similar items in EconPapers)
Pages: 36 pages
Date: 2010-10
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (7)
Downloads: (external link)
https://www.coleurope.eu/system/files_force/research-paper/beer18.pdf?download=1 (application/pdf)
Our link check indicates that this URL is bad, the error code is: 404 Not Found
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:coe:wpbeer:18
Access Statistics for this paper
More papers in Bruges European Economic Research Papers from European Economic Studies Department, College of Europe Contact information at EDIRC.
Bibliographic data for series maintained by Jessie Moerman ( this e-mail address is bad, please contact ).