Dynamic order acceptance and capacity planning in a stochastic multi-project environment with a bottleneck resource
Philipp Melchiors,
Roel Leus,
Stefan Creemers and
Rainer Kolisch
Additional contact information
Stefan Creemers: LEM - Lille économie management - UMR 9221 - UA - Université d'Artois - UCL - Université catholique de Lille - Université de Lille - CNRS - Centre National de la Recherche Scientifique
Post-Print from HAL
Abstract:
We study the integration of order acceptance and capacity planning in multi-project environments with dynamically arriving projects. We model this planning problem as a continuous-time Markov decision process to determine long-term optimal decisions. We examine whether macro-process planning should be performed before or after order acceptance. We characterise the structure of optimal policies, and explore the dependence on a number of parameters such as project payoff, project cost and order arrival time. We also look into the effects of set-up costs and the use of non-regular capacity.
Keywords: order acceptance; capacity planning; multi-project scheduling; Markov decision processes; dynamic arrivals (search for similar items in EconPapers)
Date: 2017-10-31
References: Add references at CitEc
Citations:
Published in International Journal of Production Research, 2017, 56 (1-2), pp.459-475. ⟨10.1080/00207543.2018.1431417⟩
There are no downloads for this item, see the EconPapers FAQ for hints about obtaining it.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:hal:journl:hal-02991018
DOI: 10.1080/00207543.2018.1431417
Access Statistics for this paper
More papers in Post-Print from HAL
Bibliographic data for series maintained by CCSD ().