Cost overruns in Swedish infrastructure projects
Jonas Eliasson ()
MPRA Paper from University Library of Munich, Germany
Abstract:
This paper explores the accuracy of cost estimates at different planning stages for Swedish transport infrastructure projects 2004-2022. Changes in project costs are tracked between the national investment plans established in 2010, 2014, 2018 and 2022. Cost estimates tend to increase considerably during the planning stages on average, while cost estimates at start of construction do not deviate systematically from final costs. The distributions of cost escalations between subsequent investment plans are highly skewed, with modes close to zero, but means in the order of 20-30 percent for projects in the planning stages. Average cost escalations are larger for rail projects than for road projects. The paper also briefly describes the Swedish infrastructure planning and decision process, summarizes previous Swedish studies, and discusses possible causes and remedies of cost overruns.
Keywords: cost overruns; transport infrastructure; project management; decision processes; transport policy (search for similar items in EconPapers)
JEL-codes: R42 (search for similar items in EconPapers)
Date: 2023
New Economics Papers: this item is included in nep-ppm, nep-tre and nep-ure
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
https://mpra.ub.uni-muenchen.de/120340/1/MPRA_paper_120340.pdf original version (application/pdf)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:pra:mprapa:120340
Access Statistics for this paper
More papers in MPRA Paper from University Library of Munich, Germany Ludwigstraße 33, D-80539 Munich, Germany. Contact information at EDIRC.
Bibliographic data for series maintained by Joachim Winter ().