Integrated scheduling, assembly area- and part-assignment for large scale, make-to-order assemblies

Rainer Kolisch

No 468, Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel from Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre

Abstract: The problem of scheduling multiple, large scale, make-to-order assemblies is considered. Beside "classical" precedence- and resource constraints as known from resource constrained project scheduling we take spatial resource and part availability constraints into account. The objective is to minimize the sum of the weighted tardiness. We propose a MIP-model of the problem which is a generalization of three allocation problems. Since the problem is NP-hard, a list-scheduling heuristic is proposed and evaluated on a set of benchmark instances.

Date: 1998
References: View references in EconPapers View complete reference list from CitEc
Citations:

Downloads: (external link)
https://www.econstor.eu/bitstream/10419/147575/1/manuskript_468.pdf (application/pdf)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:zbw:cauman:468

Access Statistics for this paper

More papers in Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel from Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre Contact information at EDIRC.
Bibliographic data for series maintained by ZBW - Leibniz Information Centre for Economics ().

 
Page updated 2025-03-20
Handle: RePEc:zbw:cauman:468