Integrated stochastic optimization of stope design and long-term underground mine production scheduling
Matheus Furtado e Faria,
Roussos Dimitrakopoulos and
Cláudio Lúcio Lopes Pinto
Resources Policy, 2022, vol. 78, issue C
Abstract:
In the commonly used underground mine planning framework, mine design is first established and is the main input for the subsequent long-term mine production scheduling optimization. This sequential optimization approach cannot, therefore, capture the synergies between the involved planning steps, generating solutions that depart substantially from a global optimum. In addition, traditional underground mine planning methods for stope design and life-of-mine production scheduling are deterministic and are based on a single estimated orebody model. As a result, the uncertainty and variability in grades and material types are not incorporated into the optimization process, resulting in designs that misrepresent all high-, medium- and low-grade stoping volumes and production schedules with misleading forecasts. A two-stage stochastic integer program (SIP) for integrated optimization of stope and development network designs and an underground mine production scheduling are proposed for the sublevel open stoping mining method under grade uncertainty and variability, quantified by a set of geostatistical simulations of the mineral deposit considered. Assuming a mine is accessed through a shaft, the model defines a schedule of levels and stopes, which aims to maximize the discounted revenues, minimize development costs, and manage the risk of not meeting production targets, while satisfying geotechnical constraints. The practical aspects of the proposed method are presented through an application at an underground gold mine. A comparison with the stepwise framework, where the stope design is input to a subsequent optimization of the production schedule, shows that the proposed approach provides a physically different design and production schedule with an 11% higher net present value (NPV) and a life-of-mine that is two years shorter, affirming the advantages of the integrated optimization process.
Keywords: Underground mining; Stope design optimization; Underground mine production scheduling; Stochastic integer programming; Geological uncertainty; Sublevel stoping (search for similar items in EconPapers)
Date: 2022
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0301420722003622
Full text for ScienceDirect subscribers only
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eee:jrpoli:v:78:y:2022:i:c:s0301420722003622
DOI: 10.1016/j.resourpol.2022.102918
Access Statistics for this article
Resources Policy is currently edited by R. G. Eggert
More articles in Resources Policy from Elsevier
Bibliographic data for series maintained by Catherine Liu ().