Construction Time Estimation Function for Canadian Utility Scale Power Plants
Herve Kabanda,
Alex Romard,
Fuze Yurtsever,
Anjali Wadhera,
Joshua Andrews and
Craig Merrett
Additional contact information
Herve Kabanda: Department of Mechanical and Aerospace Engineering, Carleton University, Ottawa, ON K1S 5B6, Canada
Alex Romard: Department of Mechanical and Aerospace Engineering, Carleton University, Ottawa, ON K1S 5B6, Canada
Fuze Yurtsever: Department of Mechanical and Aerospace Engineering, Carleton University, Ottawa, ON K1S 5B6, Canada
Anjali Wadhera: Department of Mechanical and Aerospace Engineering, Carleton University, Ottawa, ON K1S 5B6, Canada
Joshua Andrews: Department of Mechanical and Aerospace Engineering, Carleton University, Ottawa, ON K1S 5B6, Canada
Craig Merrett: Department of Mechanical and Aerospace Engineering, Carleton University, Ottawa, ON K1S 5B6, Canada
Energies, 2021, vol. 14, issue 17, 1-16
Abstract:
Construction time and time overruns for infrastructure projects have been frequently studied; however, the construction time of power plants has not been studied. This lack of study is problematic, as more renewable energy power plants, such as wind and solar, are planned for many jurisdictions. Accurately estimating the construction time of a power plant will assist construction planning, budget estimates, and policy development encouraging the use of more renewable sources. The construction times of utility scale power plants in Canada were studied using publicly available data. Multiple linear regression analysis techniques were applied to the data to generate construction time estimation functions for all power plants together, and for individual technologies. The analyses reveal that construction time is sensitive to jurisdiction and the decade of construction, indicating that decisions made by individual Canadian provincial governments at different times had statistically significant impacts on construction time. The analyses also indicated that construction time is a strong function of installed capacity, independent of technology. This finding suggests that large solar or wind energy facilities will encounter longer construction times similar to large hydroelectric facilities.
Keywords: construction planning; delays in power plant construction; grid integration of renewable energy; nuclear power; hydroelectric power (search for similar items in EconPapers)
JEL-codes: Q Q0 Q4 Q40 Q41 Q42 Q43 Q47 Q48 Q49 (search for similar items in EconPapers)
Date: 2021
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
https://www.mdpi.com/1996-1073/14/17/5421/pdf (application/pdf)
https://www.mdpi.com/1996-1073/14/17/5421/ (text/html)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:gam:jeners:v:14:y:2021:i:17:p:5421-:d:626232
Access Statistics for this article
Energies is currently edited by Ms. Agatha Cao
More articles in Energies from MDPI
Bibliographic data for series maintained by MDPI Indexing Manager ().