Onshore Oil and Gas Design Schedule Management Process Through Time-Impact Simulations Analyses
Daekyoung Yi,
Eul-Bum Lee and
Junyong Ahn
Additional contact information
Daekyoung Yi: Dae-Woo Engineering and Construction Co., Project Management Team, 75 Saemunan-Ro, Jongro-Ku, Seoul 03182, Korea
Eul-Bum Lee: Graduate Institute of Ferrous Technology (GIFT), Pohang University of Science and Technology (POSTECH), 77 Cheongam-Ro, Nam-Ku, Pohang 37673, Korea
Junyong Ahn: Florida Institute of Technology, 150 West University Blvd., Melbourne, FL 32901, USA
Sustainability, 2019, vol. 11, issue 6, 1-19
Abstract:
Korean oil and gas contractors have recently incurred significant losses due to improper engineering performance on EPC (engineering procurement and construction) projects in overseas markets. Several previous studies have verified the significant impact engineering has on EPC construction cost and project lifecycle. However, no literature has studied the time impact engineering has on EPC projects, representing a gap in the existing body of knowledge. To fill this gap, a Monte Carlo simulation was performed with the Pertmaster, Primavera risk analysis software for three sample onshore oil and gas projects. From said simulation of all major EPC critical activities, the authors found that the engineering phase is up to 10 times as impactful as the procurement and construction phases on the overall schedule duration. In assessing the engineering activities, the authors found the piping design activities to have the greatest impact on the overall schedule performance. Using these findings, the authors present a design schedule management process which minimizes the delays of project completion in EPC projects. Said process includes the following six steps: (1) Milestone management, (2) drawing status management, (3) productivity management of engineering, (4) interface management, (5) management of major vendor documents, and (6) work front management. The findings of this paper add to the body of knowledge by confirming the design phase to be the most impactful on the overall project schedule success. Furthermore, the presented design schedule management will aid industry with successfully executing the design phase in a timely manner, including examples from case study projects for a greater understanding.
Keywords: EPC; design management; scheduling analysis; Monte Carlo simulation; time-impact analysis; piping engineering; risk analysis (search for similar items in EconPapers)
JEL-codes: O13 Q Q0 Q2 Q3 Q5 Q56 (search for similar items in EconPapers)
Date: 2019
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (4)
Downloads: (external link)
https://www.mdpi.com/2071-1050/11/6/1613/pdf (application/pdf)
https://www.mdpi.com/2071-1050/11/6/1613/ (text/html)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:gam:jsusta:v:11:y:2019:i:6:p:1613-:d:214672
Access Statistics for this article
Sustainability is currently edited by Ms. Alexandra Wu
More articles in Sustainability from MDPI
Bibliographic data for series maintained by MDPI Indexing Manager ().