Prediction of Cost Overrun Risk in Construction Projects

Edyta Plebankiewicz and Damian Wieczorek
Additional contact information
Edyta Plebankiewicz: Division of Management in Civil Engineering, Faculty of Civil Engineering, Cracow University of Technology, 31-155 Kraków, Poland
Damian Wieczorek: Division of Management in Civil Engineering, Faculty of Civil Engineering, Cracow University of Technology, 31-155 Kraków, Poland

Sustainability, 2020, vol. 12, issue 22, 1-15

Abstract: The paper proposes a cost overrun risks prediction model, the structure of which is based on the fuzzy inference model of Mamdani. The model consists of numerous inputs and one output (MISO, multi-input-single-output), based on processes running consecutively in three blocks (the fuzzy block, the interference block, and the block of sharpening the representative output value). The input variables of the model include the share of element costs in the building costs ( SE ), predicted changes in the number of works ( WC ), and expected changes in the unit price ( PC ). The developed rule base makes it possible to determine the risk of cost overruns in the following categories: “very low”, “quite low”, “average”, “quite high”, and “very high”. Twenty-seven rules were assumed in the interference block. The operation of the model was illustrated by the example of selected elements of a road object and was validated by checking the correctness of the assumptions made at the design stage of the inference block rule base. It has been proven that with the increase of the share of element costs in the building costs ( SE ), predicted changes in the number of works ( WC ), and expected changes in the unit price ( PC ), the value of the risk exceeding the costs of a given element of the construction project ( R ) increases naturally and smoothly. It was emphasized in the conclusions that the cost overrun risks prediction model is intended for general contractors who subcontract many stages of works to their subcontractors in accordance with the agreed division into work elements.

Keywords: cost overrun; construction project; fuzzy sets; fuzzy inference model of Mamdani (search for similar items in EconPapers)
JEL-codes: O13 Q Q0 Q2 Q3 Q5 Q56 (search for similar items in EconPapers)
Date: 2020
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (1)

Downloads: (external link)
https://www.mdpi.com/2071-1050/12/22/9341/pdf (application/pdf)
https://www.mdpi.com/2071-1050/12/22/9341/ (text/html)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:gam:jsusta:v:12:y:2020:i:22:p:9341-:d:442837

Access Statistics for this article

Sustainability is currently edited by Ms. Alexandra Wu

More articles in Sustainability from MDPI
Bibliographic data for series maintained by MDPI Indexing Manager ().

 
Page updated 2025-03-19
Handle: RePEc:gam:jsusta:v:12:y:2020:i:22:p:9341-:d:442837