Are We Building Too Much Natural Gas Pipeline? A comparison of actual US expansion of pipeline to an optimized plan of the interstate network

Thuy Doan, Matthias Fripp and Michael Roberts
Additional contact information
Thuy Doan: UHERO and Department of Economics, University of Hawai'i at Manoa
Matthias Fripp: UHERO

No 2022-2, Working Papers from University of Hawaii Economic Research Organization, University of Hawaii at Manoa

Abstract: Interstate natural gas transmission and storage infrastructure is facilitated using regulated, private transactions. Pipeline companies obtain long-term contracts from producers and wholesale purchasers, typically local distribution companies (LDCs). Historically, the Federal Energy Regulatory Commission (FERC) accepted these counterparty contracts as sufficient justification of need. Typically the LDCs are themselves regulated firms, which sometimes possess affiliations with pipeline companies. But with contracted costs largely passed through to retail customers via regulated prices, it is unclear whether contracting parties face sufficient competition or otherwise possess an incentive to find least-cost alternatives. To aid evaluation of past and future investments, we develop a national-level optimization model that can assess the need for new interstate pipeline and storage facilities. The model takes production and demand pathways as fixed and minimizes the infrastructure and operation costs of transport and storage in order to balance supply and demand on each day in each state. Transport of gas can be achieved using pipeline transmission of dry gas, or using truck or ship transport of liquefied natural gas (LNG), and optimal placement of liquefaction and gasification facilities. The model also accounts for international imports and exports of both dry gas and LNG. Three underground drygas storage facilities are considered, as well as LNG storage. We compare the model’s optimized plan with observed outcomes as the sector grew rapidly with hydraulic fracturing. We find that the U.S. has built 38 percent more pipeline and 27 percent more underground storage than necessary, amounting to roughly $179 billion in excess investment. It would have been more economic to expand pipeline far less than observed and instead satisfy critical-peak demands for gas using LNG, plus necessary liquefaction and gasification facilities. Differences between optimized and observed investments vary across the interstate network, while flows between states and into and out of storage bear a close resemblance to observed outcomes.

Keywords: C61; L52; Q49 (search for similar items in EconPapers)
Pages: 56 pages
Date: 2022-04
New Economics Papers: this item is included in nep-cta, nep-ene and nep-reg
References: View references in EconPapers View complete reference list from CitEc
Citations:

Downloads: (external link)
https://uhero.hawaii.edu/wp-content/uploads/2022/04/UHEROwp2202.pdf First version, 2022 (application/pdf)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:hae:wpaper:2022-2

Access Statistics for this paper

More papers in Working Papers from University of Hawaii Economic Research Organization, University of Hawaii at Manoa Contact information at EDIRC.
Bibliographic data for series maintained by UHERO (uhero@hawaii.edu).

 
Page updated 2025-03-30
Handle: RePEc:hae:wpaper:2022-2