On path floats in a stochastic project network
Ching-Chung Kuo,
Zhen Li and
Jun Ma
International Journal of Applied Management Science, 2014, vol. 6, issue 2, 136-151
Abstract:
In a deterministic project network, all the activity times are fixed values and the path float can be found by computing the difference between the project duration and the path length. This is not possible in its stochastic counterpart, where the path lengths and the project duration change constantly since each activity time is a random variable. In the current literature, several methods have been proposed to define the float of a path in this case but all of them are fundamentally flawed. This paper aims to suggest an improved definition of path float in a stochastic project network and show how to compute it through the use of an approximation algorithm for estimating the mean and variance of the project duration under some reasonable assumptions. A numerical example will be provided to demonstrate the superiority of the new approach to the existing ones.
Keywords: project management; stochastic project networks; critical path; path float; normal distribution. (search for similar items in EconPapers)
Date: 2014
References: Add references at CitEc
Citations: View citations in EconPapers (1)
Downloads: (external link)
http://www.inderscience.com/link.php?id=60890 (text/html)
Access to full text is restricted to subscribers.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:ids:injams:v:6:y:2014:i:2:p:136-151
Access Statistics for this article
More articles in International Journal of Applied Management Science from Inderscience Enterprises Ltd
Bibliographic data for series maintained by Sarah Parker ().