Subjective Time Estimates in Critical Path Planning--A Preliminary Analysis

William R. King and Talmadge A. Wilson
Additional contact information
William R. King: Air Force Institute of Technology
Talmadge A. Wilson: USAF Systems Command

Management Science, 1967, vol. 13, issue 5, 307-320

Abstract: A historical analysis of activity time estimates made by a number of contractors on a large-scale systems development project is conducted using two basic hypotheses. (1) Pre-activity time estimating accuracy improves as the beginning date of the activity approaches. (2) Time estimates made during the progress of an activity improve in relative accuracy as the completion date of the activity approaches. These hypotheses are tested and several models for adjusting time estimates on the basis of the estimator's past history are developed and tested. The results are not proposed to be definitive--but rather, preliminary ones which should serve to demonstrate the feasibility of the basic approach.

Date: 1967
References: Add references at CitEc
Citations: View citations in EconPapers (3)

Downloads: (external link)
http://dx.doi.org/10.1287/mnsc.13.5.307 (application/pdf)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:inm:ormnsc:v:13:y:1967:i:5:p:307-320

Access Statistics for this article

More articles in Management Science from INFORMS Contact information at EDIRC.
Bibliographic data for series maintained by Chris Asher ().

 
Page updated 2025-03-19
Handle: RePEc:inm:ormnsc:v:13:y:1967:i:5:p:307-320