The impact of lot splitting on lead times in a deterministic production line
Inneke van Nieuwenhuyse and
Nico Vandaele
Working Papers from University of Antwerp, Faculty of Business and Economics
Abstract:
It is generally known that the mechanism of overlapping operations allows to reduce the average job lead times in a production system. However, a machine may remain idle between two consecutive sublots belonging to the same job, due to a difference between its own setup and processing times and those of the preceding machine. These idle times are referred to as “gaps”. Until now, little formal results are available to calculate these “gaps” in terms of the system parameters and the transfer batch sizes used. In this paper, we derive expressions for these gaps and the transfer batch lead times in a single-product production line with deterministic arrivals, setup and processing times. We prove that in our setting, the average transfer batch lead time is minimized when the transfer batch size equals one product unit.
Keywords: Transfer batching; Overlapping operations; Lead time management (search for similar items in EconPapers)
Pages: 18 pages
References: Add references at CitEc
Citations:
Downloads: (external link)
https://repository.uantwerpen.be/docman/irua/983878/26f9a891.pdf (application/pdf)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:ant:wpaper:2003006
Access Statistics for this paper
More papers in Working Papers from University of Antwerp, Faculty of Business and Economics Contact information at EDIRC.
Bibliographic data for series maintained by Joeri Nys ().