EconPapers    
Economics at your fingertips  
 

Contingency in nuclear power plant decommissioning cost estimation

Geoffrey Rothwell

Energy Economics, 2025, vol. 149, issue C

Abstract: Hundreds of estimates have been made of decommissioning costs for commercial nuclear power plants. There is no standard method for making these estimates, particularly for estimating contingency, a type of risk premium, to cover unexpected costs during project execution. Following cost engineering guidelines for estimating contingency requires, among other project characteristics, consideration of (1) the cost estimate's probability distribution, (2) the cost estimate's variance, (3) the estimator's assumed accuracy range that will contain the final cost, (4) the estimator's level of confidence that the final cost will be in the stated accuracy range, and (5) the cost estimate user's risk aversion. The variance (or standard deviation) can be calculated using Monte Carlo techniques, which generally assume no correlation between individual activity costs. Because of portfolio effects, the simulated standard deviation of the aggregated activity cost is smaller than what would be suggested by nuclear decommissioning cost estimating guidelines. The simulated standard deviation is more reasonable when correlations are assumed to be non-zero between activities. This conclusion is shown by applying the proposed method for estimating contingency to activity costs estimated by the decommissioning operations contractor EnergySolutions to decommission the Kewaunee nuclear power plant in Wisconsin, while it is decommissioning four other US nuclear power units after it completed the decontamination and demolition of four units, including Zion 1&2. EnergySolutions could be approaching Nth-of-a-Kind decommissioning costs for US nuclear power plants, thus cost uncertainty should decrease.

Keywords: Decontamination and Demolition; SAFSTOR; DECON; Estimating uncertainty; Monte Carlo simulation; Extreme value distribution; Gumbel; Constant absolute risk aversion (search for similar items in EconPapers)
JEL-codes: C63 D81 L74 L94 O38 Q42 (search for similar items in EconPapers)
Date: 2025
References: Add references at CitEc
Citations:

Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0140988325005481
Full text for ScienceDirect subscribers only

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:eee:eneeco:v:149:y:2025:i:c:s0140988325005481

DOI: 10.1016/j.eneco.2025.108721

Access Statistics for this article

Energy Economics is currently edited by R. S. J. Tol, Beng Ang, Lance Bachmeier, Perry Sadorsky, Ugur Soytas and J. P. Weyant

More articles in Energy Economics from Elsevier
Bibliographic data for series maintained by Catherine Liu ().

 
Page updated 2025-09-09
Handle: RePEc:eee:eneeco:v:149:y:2025:i:c:s0140988325005481