James Burns and Qing Cao

International Journal of Project Organisation and Management, 2011, vol. 3, issue 1, 1-21

Abstract: New deterministic, path-sensitive approaches to tracking and control are presented that will provide assessments of on-time as well as within-budget completion, taking into consideration the critical path. Project management and control with earned value analysis (EVA) is first investigated for validity. EVA is well-accepted as a technique for performance measurement of projects during execution. Even so, limitations are found and catalogued for projects of all sizes. From those limitations, improvements are proposed, such improvements taking the form of simple heuristics involving paths. The improvements are tested and found to have validity.

Keywords: earned value management; EVM; earned value analysis; EVA; critical paths; budget at completion; BAC; time at completion; TAC; critical chain project management; CCPM; path-sensitive heuristics; deterministic heuristics; project tracking; project control; performance measurement; project organisation. (search for similar items in EconPapers)
Date: 2011
References: Add references at CitEc
Citations: View citations in EconPapers (2)

Downloads: (external link)
http://www.inderscience.com/link.php?id=38861 (text/html)
Access to full text is restricted to subscribers.

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:ids:ijpoma:v:3:y:2011:i:1:p:1-21

Access Statistics for this article

More articles in International Journal of Project Organisation and Management from Inderscience Enterprises Ltd
Bibliographic data for series maintained by Sarah Parker ().

 
Page updated 2025-03-19
Handle: RePEc:ids:ijpoma:v:3:y:2011:i:1:p:1-21