The Bi-Criterial Approach to Project Cost and Schedule Buffers Sizing
Paweł Błaszczyk (),
Tomasz Błaszczyk () and
Maria B. Kania ()
Additional contact information
Paweł Błaszczyk: University of Silesia
Tomasz Błaszczyk: University of Economics in Katowice
Maria B. Kania: University of Silesia
Chapter Chapter 9 in New State of MCDM in the 21st Century, 2011, pp 105-114 from Springer
Abstract:
Abstract The aim of this research was the trial of modelling and optimizing the time-cost trade-offs in project planning problem with taking into account the behavioral impact of performers’ (or subcontractors’) estimations of basic activity parameters. However, such a model must include quantitative measurements of budget and duration, so we proposed to quantify and minimize the apprehension of their underestimations. The base of the problem description contains both safe and reasonable amounts of work estimations and the influence factors matrix. We assumed also the pricing opportunity of performance improving. Theoretical considerations were examined in several examples solved in spreadsheet environment.
Keywords: Buffer management; Project planning; Time-cost trade-off (search for similar items in EconPapers)
Date: 2011
References: Add references at CitEc
Citations:
There are no downloads for this item, see the EconPapers FAQ for hints about obtaining it.
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:spr:lnechp:978-3-642-19695-9_9
Ordering information: This item can be ordered from
http://www.springer.com/9783642196959
DOI: 10.1007/978-3-642-19695-9_9
Access Statistics for this chapter
More chapters in Lecture Notes in Economics and Mathematical Systems from Springer
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().