GRASP and path relinking for project scheduling under partially renewable resources

R. Alvarez-Valdes, E. Crespo, J.M. Tamarit and F. Villa

European Journal of Operational Research, 2008, vol. 189, issue 3, 1153-1170

Abstract: Recently, in the field of project scheduling problems the concept of partially renewable resources has been introduced. Theoretically, it is a generalization of both renewable and non-renewable resources. From an applied point of view, partially renewable resources allow us to model a large variety of situations that do not fit into classical models, but can be found in real problems in timetabling and labor scheduling. In this paper, we develop some preprocessing techniques and several heuristic algorithms for the problem. Preprocessing significantly reduces the dimension of the problems, therefore improving the efficiency of solution procedures. Heuristic algorithms based on GRASP and Path relinking are then developed and tested on existing test instances, obtaining excellent results.

Date: 2008
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (12)

Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0377-2217(07)00591-7
Full text for ScienceDirect subscribers only

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:eee:ejores:v:189:y:2008:i:3:p:1153-1170

Access Statistics for this article

European Journal of Operational Research is currently edited by Roman Slowinski, Jesus Artalejo, Jean-Charles. Billaut, Robert Dyson and Lorenzo Peccati

More articles in European Journal of Operational Research from Elsevier
Bibliographic data for series maintained by Catherine Liu ().

 
Page updated 2025-03-19
Handle: RePEc:eee:ejores:v:189:y:2008:i:3:p:1153-1170