On path correlation and PERT bias
Arunava Banerjee and
Anand Paul
European Journal of Operational Research, 2008, vol. 189, issue 3, 1208-1216
Abstract:
Most studies of project time estimation assume that (a) activity times are mutually independent random variables; many also assume that (b) path completion times are mutually independent. In this paper, we subject the impact of both these assumptions to close scrutiny. Using tools from multivariate analysis, we make a theoretical study of the direction of the error in the classical PERT method of estimating mean project completion time when correlation is ignored. We also investigate the effect of activity dependence on the normality of path length via simulation.
Date: 2008
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (1)
Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0377-2217(07)00594-2
Full text for ScienceDirect subscribers only
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eee:ejores:v:189:y:2008:i:3:p:1208-1216
Access Statistics for this article
European Journal of Operational Research is currently edited by Roman Slowinski, Jesus Artalejo, Jean-Charles. Billaut, Robert Dyson and Lorenzo Peccati
More articles in European Journal of Operational Research from Elsevier
Bibliographic data for series maintained by Catherine Liu ().