Project scheduling with generalized precedence relations: A new method to analyze criticalities and flexibilities

Lucio Bianco, Massimiliano Caramia and Stefano Giordani

European Journal of Operational Research, 2022, vol. 298, issue 2, 451-462

Abstract: In this paper, we illustrate a new method to overcome the failures of the theory proposed by Elmaghraby and Kamburowski (1992) and De Reyck (1998) for the analysis of activity criticalities and flexibilities in non-preemptive project scheduling with generalized precedence relations under unlimited resources. These failures, discussed in detail in this paper, call for a new approach to study this problem. We provide new definitions of criticalities and consequently new tools for their identification within a more general framework without ambiguities.

Keywords: Project scheduling; Critical path; Flexibility analysis; Generalized precedence relations (search for similar items in EconPapers)
Date: 2022
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (1)

Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0377221721006172
Full text for ScienceDirect subscribers only

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:eee:ejores:v:298:y:2022:i:2:p:451-462

DOI: 10.1016/j.ejor.2021.07.022

Access Statistics for this article

European Journal of Operational Research is currently edited by Roman Slowinski, Jesus Artalejo, Jean-Charles. Billaut, Robert Dyson and Lorenzo Peccati

More articles in European Journal of Operational Research from Elsevier
Bibliographic data for series maintained by Catherine Liu ().

 
Page updated 2025-03-19
Handle: RePEc:eee:ejores:v:298:y:2022:i:2:p:451-462