Automatic selection of the best performing control point approach for project control with resource constraints
Jie Song,
Jinbo Song and
Mario Vanhoucke
European Journal of Operational Research, 2025, vol. 322, issue 1, 15-38
Abstract:
During project execution, the actual project progress shows deviations from the baseline schedule due to uncertainty. To complete the project timely, project monitoring is performed at discrete control points to identify project opportunities/problems and take possible corrective actions. These control points affect the quality of project monitoring and corrective actions, but little guidance is available on identifying situations where the control points pay off the most in terms of project duration.
Keywords: Project scheduling; Control points; Project characteristics; Classification model (search for similar items in EconPapers)
Date: 2025
References: Add references at CitEc
Citations:
Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0377221724008002
Full text for ScienceDirect subscribers only
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eee:ejores:v:322:y:2025:i:1:p:15-38
DOI: 10.1016/j.ejor.2024.10.025
Access Statistics for this article
European Journal of Operational Research is currently edited by Roman Slowinski, Jesus Artalejo, Jean-Charles. Billaut, Robert Dyson and Lorenzo Peccati
More articles in European Journal of Operational Research from Elsevier
Bibliographic data for series maintained by Catherine Liu ().