Permutation flowshop scheduling problems with time lags to minimize the weighted sum of machine completion times
J. Fondrevelle,
A. Oulamara and
M.-C. Portmann
International Journal of Production Economics, 2008, vol. 112, issue 1, 168-176
Abstract:
In this article, we consider flowshop scheduling problems with minimal and maximal time lag constraints. Such constraints extend precedence constraints between operations in the jobs and may be used to model various industrial applications. The objective is to minimize a non-classical criterion based on the weighted sum of machine completion times. We show that it generalizes makespan and we derive several complexity results for two- and three-machine problems. An exact algorithm based on a branch-and-bound procedure is developed to solve the permutation flowshop problem with m machines.
Date: 2008
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (3)
Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0925-5273(07)00136-3
Full text for ScienceDirect subscribers only
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eee:proeco:v:112:y:2008:i:1:p:168-176
Access Statistics for this article
International Journal of Production Economics is currently edited by Stefan Minner
More articles in International Journal of Production Economics from Elsevier
Bibliographic data for series maintained by Catherine Liu ().