Communication to the Editor--The Use of Subjective Probability Estimates in Assessing Project Completion Times

J. B. Kidd and J. R. Morgan
Additional contact information
J. B. Kidd: Departmental of Engineering Production, University of Birmingham
J. R. Morgan: Institute for Operational Research

Management Science, 1969, vol. 16, issue 3, 266-269

Abstract: The conclusion from this analysis supports King's [King, W. R., T. A. Wilson. 1967. Subjective time estimates in critical path planning--A preliminary analysis. Management Sci. 13(5, January) 307-320.] main point that there is little evidence of learning (i.e. improvement in the accuracy of estimates) in the period before work starts. There are, however, some differences. In this situation, more changes in estimates are made before work starts than reported by King. This is perhaps not surprising since King's analysis refers to new construction, which can perhaps be specified more clearly in advance, rather than the maintenance work which we are concerned.

Date: 1969
References: Add references at CitEc
Citations:

Downloads: (external link)
http://dx.doi.org/10.1287/mnsc.16.3.266 (application/pdf)

Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.

Export reference: BibTeX RIS (EndNote, ProCite, RefMan) HTML/Text

Persistent link: https://EconPapers.repec.org/RePEc:inm:ormnsc:v:16:y:1969:i:3:p:266-269

Access Statistics for this article

More articles in Management Science from INFORMS Contact information at EDIRC.
Bibliographic data for series maintained by Chris Asher ().

 
Page updated 2025-03-19
Handle: RePEc:inm:ormnsc:v:16:y:1969:i:3:p:266-269